Compliance audit report on the Railways in Parliament
Why in news? The Comptroller and Auditor General (CAG) of India has recently released several significant audit reports and updates. On December 18, 2025, the CAG presented its compliance audit report on the Railways in Parliament, highlighting various findings related to financial and operational performance.
Key Recent CAG Findings
The CAG flagged serious financial irregularities and delays in flagship power schemes like SAUBHAGYA and DDUGJY, including early payments to contractors, unapproved project reports, and double payments, resulting in losses amounting to crores of rupees.รขโฌโน
In the GST audit, the CAG highlighted a significant manpower crunch in the Central Board of Indirect Taxes and Customs (CBIC), with 38% of audit positions vacant as of July 2024, leading to gaps in audit coverage and recovery rates.รขโฌโน
The CAG also reported that only 122 MW of solar capacity had been installed by Coal India by December 2024, far short of the 3,000 MW target, indicating major delays in renewable energy rollout.รขโฌโน
SAUBHAGYA (Pradhan Mantri Sahaj Bijli Har Ghar Yojana)
Launch Year: 2017
Objective:Universal household electrification across rural & urban India.
Key Features:
Free electricity connections to poor households (identified via SECC 2011).
Last-mile connectivity through extension of wires, meters, LED bulb, mobile charging point.
Provision for solar power packs in remote areas.
Achievement: Over 2.82 crore households electrified till March 2021.